Sanko Holding Administrative Building
The Holding Building project, which is designed to be constructed in Erikce Location of Gaziantep Province, is designed to relocate the head office located in Gazikent to this area. The administrative building consists of 2 blocks with a gross usage area of 34,000 m2 and a construction area of 19,300 m2. The last two floors of both blocks are supported by composite steel slabs. Main stairs and fire escapes are also designed as steel system. In the interior, many different constructions such as wood, marble, raised flooring, vinyl-tile-ceramic coating, carpet tiles, smart glass film covered separator glass partitions were constructed.
The administrative building is the first LEED certified office building in Gaziantep. The project utilizes 100% renewable energy and is constructed in accordance with high acoustic and air quality standards.
Within the scope of the project, 23,500 m3 of concrete, 3,200 tons of rebars, 1,200 m2 of glass, 3,600 m2 of roofing and 600 tons of steel were used.
-
Project StatusCompleted
-
EmployerSanko Holding
-
Country CityTürkiye, Gaziantep
-
Year of Construction2013 - 2023
-
Project Duration30 Months
-
Main ItemsSurvey, Design, Construction
-
Project DetailsSuperstructure Projects
-
Akyel 1 and Akyel 2 Wind Power Plant Hybrid Solar Energy Power Plant (GES) Project
Karaman -
Koclu Hydroelectric Plant (HES) Regulator/ Power Plant Region Modification and New Construction Works
Giresun -
Cimko Cimento Adiyaman Branch Preheater Building Reinforcement Work
Adıyaman -
Flake Washing Facility Construction
Bursa -
Gazi-9 Wind Power Plant
Çanakkale -
Gaziantep Basak Traktor Solar Energy Power Plant (GES) Project
Gaziantep -
Guney-1 Wind power plant
Bursa -
ISKO14 Denim Weaving Building
Bursa -
POY Facility Construction
Bursa -
Sanko University Ahi Cafe Project
Gaziantep -
Sanko Adiyaman Solar Energy Power Plant (GES) Project
Adıyaman -
Sanko Tekstil Baspinar-1 Solar Energy Power Plant (GES) Project
Gaziantep -
Sanko Tekstil Baspinar-2 Solar Energy Power Plant (GES) Project
Gaziantep -
Sanko Tekstil Towel Solar Energy Power Plant (GES) Project
Gaziantep -
Isko Solar Energy Power Plant (GES)-1 Project
Bursa -
Sanko Tekstil Blue Collar Social Reinforcement Renovation
Adıyaman -
Super Film Solar Energy Power Plant-1 (GES-1) and Solar Energy Power Plant-2 (GES-2) Project
Gaziantep -
Sanko Superair Hangar Project
Gaziantep -
Cimko Cimento Taslica Ready Mixed Concrete Plant
Gaziantep -
Construction of ISKO Crisps Production Factory
Bursa -
Construction of Akyel 2 Hybrid SPP
Karaman -
Desa Deri Duzce SPP Project
Düzce -
Sanko Tekstil New Cotton Warehouse
Adıyaman -
Modification Works and Trench Works for Sanko Enerji Kalkandere HEPP Y4 Approach Tunnel
Rize -
Salihli Kurtulus Bazaar
Manisa -
Sanko Havlu Additional Building and Warehouse Project
Gaziantep -
Construction of Sanko Tekstil Cotton Warehouse
Adıyaman -
Superfilm Metalized 6 Warehouse Construction
Gaziantep -
Sanko Petrokimya Golovasi Port Facilities Phase-3 Wharf Construction
Adana -
Sanko Tekstil Isletmeleri San. Ve Tic. A.S
Adıyaman -
Sanko Tekstil Fiber Recycling Facility
Gaziantep -
Superfilm Metalized-6 Plant
Gaziantep -
Sanko Universitesi Hastanesi (Sanko University Hospital) Renovation Project
Gaziantep -
Akyel - 1 Hybrid SPP Project
Karaman -
Carchemish Ancient City Roofing Project
Gaziantep -
Kutnia Showroom Store
Gaziantep -
Sanko Tekstil Prefabricated Building Project
Adıyaman -
Sanko Enerji Koclu HEPP Guidance Wall
Giresun -
July 15 Temporary Housing Project
-
Sanko Tekstil Organized Industrial Zone (OSB) Region 4 Investment Project
Gaziantep -
Superfilm Administrative Building Renovation Project
Gaziantep